csatmedium

Ram and Shyam work on a job together for four days and complete 60% of it. Ram takes leave then and Shyam works for eight more days to complete the job. How long would Ram take to complete the entire job alone ?

  1. A.6 days
  2. B.8 days
  3. C.10 days
  4. D.11 days
▶ Answer & Explanation

Correct answer: C. 10 days

If Ram and Shyam complete 60% of the job in 4 days, they complete 15% per day. The remaining 40% is completed by Shyam alone in 8 days, meaning Shyam completes 5% of the job per day. Since together they complete 15% per day, Ram must complete 10% of the job per day. Therefore, Ram would take 10 days to complete the entire job alone.