24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?

  1. A.30 days
  2. B.More than 30 days
  3. C.Less than 30 days or more than 30 days
  4. D.Data is inadequate to draw any conclusion
▶ Answer & Explanation

Correct answer: D. Data is inadequate to draw any conclusion

To solve this problem, we need to establish the relative working capacity of men and women. Let's assume a man's work rate is 'm' and a woman's work rate is 'w'. The total work done by 24 men and 12 women in 30 days is (24m + 12w) * 30. We need to find the days (let's call it 'D') for 12 men and 24 women to do the same work, which is (12m + 24w) * D. For D to be determinable, the ratio of work rates (m/w) must be constant and known or derivable from the problem statement. Without information on the comparative efficiency of men and women, we cannot set up a solvable equation.

Source: UPSC csat 2022

Practice this question with answer tracking

Track your performance, build spaced repetition reviews, and see your weak areas.

Start practising free →